Projects | an overview including Mining, Rail, Highway, Construction

Projects

Kicking Horse Canyon - Snow Nets

CONSTRUCTION TIMELINE: May—Sept 2016 (Phase I) Spring 2017 (Phase II)   SCOPE: Snow Net Installation 2000m of Snow Nets within 6 months on the steep slopes of the Rocky Mountains.   OWNER:...

READ MORE

Highland Valley Copper

CONSTRUCTION TIMELINE: Ongoing multi year contract SCOPE: Primary: Horizontal Drain Hole Drilling OWNER: Teck Resources PROJECT CHALLENGES: Day to day operations on such a large site requires constant and consistent...

READ MORE

Canadian Pacific Railway

CONSTRUCTION TIMELINE: 2009—Present Ongoing Contract   SCOPE: Scaling Stabilization Rockfall Mitigation Shotcrete Anchoring   OWNER: CP Rail Canada   PROJECT...

READ MORE

Columbia Icefield Skywalk

CONSTRUCTION TIMELINE: 2012—2014   SCOPE: Anchors High Angle Scaling   OWNER:   PROJECT CHALLENGES: Remote Access Congested construction site +918’ above the...

READ MORE

Rio Tinto - Diavik Diamond Mine, Northwest Territories

CONSTRUCTION TIMELINE: Since 2008   SCOPE: Scaling Drilling Installation of Mesh Systems Trim Blasting   BUDGET: Various   OWNER: Rio Tinto and Dominion Diamond ...

READ MORE

Dominion Diamonds Corp.- Ekati Mine, Northwest Territories

The Ekati (Diamond) Mine Canada’s first diamond mine and is part of the Diavik Diamond Mine complex. It is one of the most remote mines in the world, located on the bed of a vast northern lake, Lac de Gras….300 kilometers...

READ MORE

AltaGas - Forrest Kerr Run-of-River Hydroelectric Project

BAT Construction Ltd. performed Slope Stabilization processes, such as rock bolting, curtain grouting, screening and shotcrete at the 195MW Forrest Kerr Run-of-River hydroelectric project located on the Iskut River in British Columbia,...

READ MORE

Thompson Rivers University

2011

BAT Construction was part of the expansion of the student activity centre by installing DCP seismic anchors.

READ MORE

Elkview Coal Operations

2008 and 2010 BAT Construction has been working closely with Teck Coal Limited at their Elkview Coal Operations since 2008. As well as our ongoing work, BAT has completed two very large projects that include external and internal...

READ MORE

Alterra Power

2008 BAT Construction assisted Golders with testing of anchors at Alterra's Dokie Ridge.                            ...

READ MORE

Kettle Valley Rock Scaling using Rope Access

CONSTRUCTION TIMELINE:  March 2021   SCOPE: Rope Access Scaling   OWNER: Regional District of Okanagan Similkameen    BAT Construction Ltd. Was tasked with rock scaling using...

READ MORE

Bell 2 Towers - BC Hydro

CONSTRUCTION TIMELINE: 2020   SCOPE: Structure Anchors Drilling Grouting Testing   OWNER: BC Hydro General Contractor: Progressive Ventures   PROJECT CHALLENGES:...

READ MORE

CN Retaining Walls

CONSTRUCTION TIMELINE: Since 2009   SCOPE: Mitigate erosion of railway grade   BUDGET: Various   OWNER: CN Rail   PROJECT CHALLENGES: Remote Access and unstable...

READ MORE

CN Thornton Tunnel

CONSTRUCTION TIMELINE:  Dec 2020   SCOPE: Rope Access Construction   OWNER: CN Rail   PROJECT CHALLENGES: Working in a vertical shaft Not disrupting rail traffic Site...

READ MORE

Savona CS 7 Cooler Addition

CONSTRUCTION TIMELINE: March 2020—December 2020   SCOPE: Rock Fencing installations Tie Back Retaining Wall Cast-in Place Concrete Retaining Wall Cable Anchors Shotcrete    ...

READ MORE

Galore Creek Mine - Stabilization Services

CONSTRUCTION TIMELINE: 2009-Present  Annual Rock Scaling and  Stabilization services   SCOPE: Hazard Assessment/Abatement Scaling: road cuts & rock faces Rock bolting & Screening...

READ MORE